Project Overview

Installation of 2 x 100kw Worcester GB 162’s on a skid along with twin DAB pump set, pressurisation unit, magna clean, control panel, pipe and lagging.

The works for the project included:


  • Design and build of control panel
  • Installation of Gas Supply
  • Installation of Flow and Return and lag in foil back lagging
  • Installation mechanically and electrically of pressurisation unit, pumps, magna clean and solenoid valve
  • Cold water services
  • Commissioning

Project Value: £10,000 (excluding supply of boiler and plant)


Project Team

Client: CPS
Main Contractor: EcoTech
Consultant: N/A
Project Manager: Mark Hillier-Rees
Completion Date: February 2018